On 4 août 04, at 20:00, Andrew P. Black wrote:
At 10:20 +0200 2004.8.4, stéphane ducasse wrote:
Resources are normally set before any test run and teardown after all the test run if I remember correctly.
That is indeed what you imply in the tutorial;. But as far as we can see, it is not what the code does. It calls "reset", not "tearDown".
May be I refer to another version because SUnit releases are the mess.
In the tutorial I show how you can add sharedSetUp Test that do not execute setup for all the tests of a test suite but that executes it for each test suite. I really needed that and ressources were not the answer.
Are you referring to the TestSuite>>areAllResourcesAvailable" stuff?
I do not remember. I wrote that so long ago and my code refers to VW SUnit version.
We were confused because this is not what our version of SUnit does, and assumed that the documentation was out of date, not that this was a an enhancement.
I don't see how what you describe above for "sharedSetUp" is different from Resources, if they worked correctly.
A resources is initialized before **any** test runs, so one of your testsuite may invalidate the resource that is need in a certain state by another test suite. I discussed a lot with joseph about that and I will show why we need that with alan knight at ESUG. In moose for example, each test suite build a different model of a program, which is then accessed using a singleton, so the resources could not work there since testOne would run on a model that is not adequate (may be installed by the resources associated with testTwo).